CMR 2017, Chapter-2, MCQ Practice Set-3

  1. As per CMR 2017, Notice of reopening in Form 1B, shall be submitted to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. All of the above
    D. All of the above; In case of reopening of the mine, notice for intention or to communicate the actual date of reopening, Notice in Form-1B, should be given to CIM, RIM and DM.
  2. When it is intended to reopen a mine, notice of reopening in Form 1B, shall be submitted _____________ to the reopening of the Mining operations?
    A. at least 30 days earlier
    B. within 30 days
    C. within 7 days
    D. within 14 days
    A. at least 30 days earlier
  3. Notice of reopening in Form 1B, shall be submitted __________to the reopening of the Mining operations?
    A. Forthwith
    B. within 30 days
    C. within 7 days
    D. within 14 days
    A. Forthwith
  4. When a mine has been reopened, who shall forthwith communicate the actual date of reopening to the Chief Inspector, the Regional Inspector and to the District Magistrate?
    A. Only owner
    B. Only Agent
    C. Only Manager
    D. Any of the above
    D. Any of the above
  5. In Form 2A : Change in name of mine, notice shall be given to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. Only A & B
    D. Only A & B;
    फॉर्म 2 में 2 को नोटिस देना है। इसमें इन्टेन्शन वाली बात नहीं है मतलब की चेंज किए और उसके बाद सूचना भेजना है ।
  6. In Form 2B : Change of ownership, notice shall be given to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. Only A & B
    D. Only A & B;
    फॉर्म 2 में 2 को नोटिस देना है। इसमें इन्टेन्शन वाली बात नहीं है मतलब की चेंज किए और उसके बाद सूचना भेजना है ।
  7. In Form 2C : change of address of Owner, Agent or Manager, notice shall be given to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. Only A & B
    D. Only A & B;
    फॉर्म 2 में 2 को नोटिस देना है। इसमें इन्टेन्शन वाली बात नहीं है मतलब की चेंज किए और उसके बाद सूचना भेजना है ।
  8. In Form 2D : Appointment, notice shall be given to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. Only A & B
    D. Only A & B;
    फॉर्म 2 में 2 को नोटिस देना है। इसमें इन्टेन्शन वाली बात नहीं है मतलब की चेंज किए और उसके बाद सूचना भेजना है ।
  9. In Form 2E : Termination, notice shall be given to?
    A. CIM (Chief Inspector of mines)
    B. RIM (Regional Inspector of Mines)
    C. DM (District Magistrate)
    D. Only A & B
    D. Only A & B;
    फॉर्म 2 में 2 को नोटिस देना है। इसमें इन्टेन्शन वाली बात नहीं है मतलब की चेंज किए और उसके बाद सूचना भेजना है ।
  10. In Form 2A, 2B, 2C, 2D, 2E, Notice should be furnished within?
    A. Forthwith
    B. within 30 days
    C. within 7 days
    D. within 14 days
    C. within 7 days
  11. A mine belongs to public sector, one of the directors is appointed, who is also a nominated owner, then in which form the information shall be furnished?
    A. Form 2A
    B. Form 2B
    C. Form 2C
    D. Form 2D
    B. Form 2B, Hint: Director is the nominated owner and means to say the change in the ownership happened.
  12. When manager is appointed, choose the correct form for information to CIM & RIM?
    A. Form 2A
    B. Form 2B
    C. Form 2C
    D. Form 2D
    D. Form 2D
  13. When manager is terminated, choose the correct form for information to CIM & RIM?
    A. Form 2B
    B. Form 2C
    C. Form 2D
    D. Form 2E
    D. Form 2E
  14. When an assistant manager is appointed in the mines, in which form information shall be furnished to CIM, RIM?
    A. Form 2A
    B. Form 2B
    C. Form 2C
    D. Form 2D
    D. Form 2D
  15. When an assistant manager is terminated in the mines, in which form information shall be furnished to CIM, RIM?
    A. Form 2B
    B. Form 2C
    C. Form 2D
    D. Form 2E
    D. Form 2E
  16. When a surveyor is appointed in the mines, in which form information shall be furnished to CIM, RIM?
    A. Form 2A
    B. Form 2B
    C. Form 2C
    D. Form 2D
    D. Form 2D
  17. When a surveyor is terminated in the mines, in which form information shall be furnished to CIM, RIM?
    A. Form 2B
    B. Form 2C
    C. Form 2D
    D. Form 2E
    D. Form 2E
  18. Previously name of mines was Magadh OCP and now it is changed to Magadh OCM, in which form information shall be furnished to CIM, RIM?
    A. Form 2A
    B. Form 2B
    C. Form 2C
    D. Form 2D
    A. Form 2A
  19. When any appointment is made of an agent, manager, engineer, surveyor, ventilation officer, safety officer, or assistant manager or when the employment of any such person is terminated or any such person leaves the said employment, or when any change occurs in the address of any agent or manager, the owner, agent or manager shall, within ___________________days from the date of such appointment, termination or change, give to the Chief Inspector and the Regional Inspector a notice in the prescribed form.
    A. 7
    B. 14
    C. 21
    D. 30
    A. 7
  20. When a change occurs in the name or ownership of a mine or in the address of the owner, the owner, agent or manager shall, within ____________ days from the date of the change, give to the Chief Inspector and the Regional Inspector a notice in the prescribed form.
    A. 7
    B. 14
    C. 21
    D. 30
    A. 7